2025-12-01 | Increased forecast simulation asset limits
9 days ago
Changed
Forecast simulation asset constraints
Maximum values increased for battery energy storage system (BESS) parameters in forecast simulations.
GET /forecasts/forecasts/
GET /forecasts/forecasts/Modified response fields:
results[].run_asset.duration(number) - Maximum increased from 8 to 12 hoursresults[].run_asset.rated_power(number) - Maximum increased from 500 to 1000 MW
POST /forecasts/run-simulation/
POST /forecasts/run-simulation/Modified request fields:
run_asset.duration(number) - Maximum increased from 8 to 12 hoursrun_asset.rated_power(number) - Maximum increased from 500 to 1000 MW
Modified response fields:
run_asset.duration(number) - Maximum increased from 8 to 12 hoursrun_asset.rated_power(number) - Maximum increased from 500 to 1000 MW